SWAHD – Traffic Notices

  SWAHD Expansion, Edmonton 24-Hour Emergency: 1-866-364-4465

TRAFFIC UPDATES

UPDATED MARCH 05, 2021:

Please see below the traffic update in regards to the DMS Work for next week.

 SWAHD – DMS Preliminary Work

As part of the SWAHD Expansion Program, Carmack’s Subcontractor, Can-Traffic, will begin the preliminary work for the DMS installation along the Anthony Henday.

The Scope of the work include the design and the installation of four (4) new structures :

  • DMS-02, North Bound Lane , at Station 2+890, by 111St Interchange On ramp.
  • DMS-03, South Bound Lane, at Station 7+270, by Terwillegar Interchange On Ramp.
  • DMS-07, North Bound Lane, at Station 12+340, by Wedgewood Creek (before the bridge).
  • DMS-08, South Bound Lane, at Station 19+140, By 87 Ave Interchange Off ramp.

At this stage, our subcontractor will start with daylighting all the utilities in our work zone, then carry on with the Directional Coring on Monday 8th March-21.

 Traffic Impact:

Day Time Shoulder Closure :

  • (1) DMS-02: Right-Hand Shoulder Closure and Speed reduction to 80 km/h over 200 m, North Bound Lane of the Anthony Henday, at 111St Interchange On-ramp to the AHD (Stat. 2+800 to 2+900)

Lane Restriction for 4 Hours, between 11:30 to 15:30,i.e off peak hour, Speed will be reduced on both lanes , (Outside shoulder is being closed).

  • (2) DMS-03:

Right-Hand Lane Closure and Speed reduction to 80 km/h over 300 m, North Bound Lane of the Anthony Henday, at the Terwillegar Interchange Off Ramp (Stat. 7+000 to 7+300)

Lane Restriction for 4 Hours, between 9:00 to 13:00,i.e off peak hour, Speed will be reduced on both lanes , (Outside shoulder lane is being closed).

Right-Hand Lane Closure and Speed reduction to 80 km/h over 200 m, South Bound Lane of the Anthony Henday, at Terwillegar Interchange On Ramp (Stat. 7+400 to 7+200)

Lane Restriction for 4 Hours, between 11:30 to 15:30,i.e off peak hour, Speed will be reduced on both lanes , (Outside shoulder lane is being closed).

  • (3) DMS-07: Right-Hand Lane Closure and Speed reduction to 80 km/h over 400 m, North Bound Lane of the Anthony Henday, at the Wedgewood Creek Bridge (Stat. 12+200 to 12+600)

Lane Restriction for 4 Hours, between 9:00 to 13:00,i.e off peak hour, Speed will be reduced on both lanes , (Outside shoulder lane is being closed).

  • (4) DMS-08: Right-Hand Lane Closure and Speed reduction to 80 km/h over 300 m, South Bound Lane of the Anthony Henday, at the 87 Ave Interchange Off ramp (Stat. 19+000 to 19+300)

Lane Restriction for 4 Hours, between 11:00 to 15:30,i.e off peak hour, Speed will be reduced on both lanes , (Outside shoulder lane is being closed).

Duration:

  • (1) DMS-02: Operation Scheduled on 8th March 2021
  • (2) DMS-03: Operation Scheduled on 9th March 2021
  • (3) DMS-07: Operation Scheduled on 10th March 2021
  • (4) DMS-08: Operation Schedule on 10th March 2021

Steel Barriers Removal – Anthony Henday North Saskatchewan River Bridge

Carmacks’ Subcontractor has completed all the Directional Drilling Work at the North Saskatchewan Bridge. We will remove all the steel barriers in place (ensuring the safety of both our crews and traffic) at the North Saskatchewan River Bridge.

Traffic Impact:

Night Time Lane Closure :

  • (1) Left-Hand Lane Closure and Speed reduction to 60 km/h over 500 m, South Bound Lane of the Anthony Henday, at the North Sask. River Bridge (Stat. 10+000 to 10+500)

Lane Restriction for 1 Hours, between 8:00pm to 9:00pm,i.e off peak hour, Speed will be reduced on the remaining lane , (Inner lane is being closed).

  • (2) Left-Hand Lane Closure and Speed reduction to 60 km/h over 700 m, North Bound Lane of the Anthony Henday, at the North Sask. River Bridge (Stat. 10+100 to 10+800)

Lane Restriction for 1 Hours, between 9:00pm to 10:00pm,i.e off peak hour, Speed will be reduced on the remaining lane , (Inner lane is being closed).

  • (3) Right-Hand Lane Closure and Speed reduction to 60 km/h over 700 m, North Bound Lane of the Anthony Henday, at the North Sask. River Bridge (Stat. 10+100 to 10+800)

Lane Restriction for 1 Hours, between 10:00pm to 11:00pm,i.e off peak hour, Speed will be reduced on the remaining lane , (Outside lane is being closed).

Duration:

Operation scheduled for March 4th 2021

Please see update below for the next two weeks on the bridge side for traffic. Note Girder erection activities is to start Monday March 8th  at night and possibility of multiple WMD lane closure may occur in a night, but will always have traffic flowing expect noted closure times below.

** Indicates Possibility of Closure OR next sequence required (MORINING OF NOTICE)

* Indicates Weather dependent, may change/be updated

.  . Key information for 511

WHITEMUD INTERCHANGE STRUCTURE LOCATION:

Eastbound WMD: 

  • Work Activity: 0) Regular Transition Shift    1)  Girder Erection Preparation   2) Girder erection Sequence 1*   3) Girder Installation**    4) Girder Erection Sequence 2 * **    5) Girder Erection Sequence 3
  • Traffic Impact: 0) Regular Traffic pattern, in effect speed reduction (50km/hr)    1) Right Lane Closure [Nighttime]  & EB WMD Transition to SB AHD Loop Ramp Lane [Nighttime] (EB WMD Setup ONLY – TAS DWG: BF85008S-TAS-GEP-01) & EB WMD Transition to SB AHD Loop Ramp Lane [Nighttime] (TAS DWG: BF85008S-TAS-GEP-01)    2) Transitions to Ramp Lanes with Nighttime Closure [9:00PM-5:00AM] (TAS DWG: BF85008S-TAS-GEP-01)*   3)  EB WMD Transition to SB AHD Loop Ramp Lane [Nighttime]. (TAS DWG: BF85008S-TAS-GEP-01)**   4) EB WMD Transfer to WB WMD No Left Turn to NB AHD [Nighttime] (TAS DWG: BF85008S-TAS-GEP-02)* **    5) WB WMD Transfer to EB WMD (TAS DWG: BR85008S-TAS-GEP-03)* **
  • Duration: 0) February 5th –  March 30th    1) March 8th & March 9th & March 11th (8:00PM – 6:00AM)    2) March 15th (8:00PM – 6:00AM)*    3) March 16th (8:00PM – 6:00AM)**    4) March 17th (8:00PM – 6:00AM)* & March 18th (8:00PM -6:00AM)**     5) March 19th (8:00PM – 6:00AM)* **

Westbound WMD: 

  • Work Activity: 0) Regular Transition Shift    1)  Formwork Installation   2) Girder Erection Preparation   3) Girder erection Sequence 1*   4) Girder Installation**    5) Girder Erection Sequence 2 * **    6) Girder Erection Sequence 3
  • Traffic Impact: 0) Regular TAS Plan in effect speed reduction (50km/hr)    1) Left Lane Closure [Daytime 9-1] to a Right Lane Closure [Daytime 1-330]  & Right Lane Closure [Daytime]   2) Transitions to Ramp Lanes with Nighttime Closure [9:00PM-5:00AM] (WB WMD Setup ONLY -TAS DWG: BF85008S-TAS-GEP-01) & Right Lane Closure [Nighttime]  3) Transitions to Ramp Lanes with Nighttime Closure [9:00PM-5:00AM] (TAS DWG: BF85008S-TAS-GEP-01)*   4)  WB WMD Transition to NB AHD Loop Ramp Lane [Nighttime]. (TAS DWG: BF85008S-TAS-GEP-01)**   5) EB WMD Transfer to WB WMD [Nighttime] (TAS DWG: BF85008S-TAS-GEP-02)* **    6) WB WMD Transfer to EB WMD No Left Turn to SB AHD (TAS DWG: BR85008S-TAS-GEP-03)* **
  • Duration: 0) March 5th –  March 30th    1) March 8th (9:00AM – 3:30PM)  &  March 9th – 10th (9:00AM – 3:30PM)    2) March 10th & 11th  (8:00PM – 6:00AM)    3) March 15th (8:00PM – 6:00AM)*    4) March 16th (8:00PM – 6:00AM)**    5) March 17th (8:00PM – 6:00AM)* & March 18th (8:00PM -6:00AM)**     6) March 19th (8:00PM – 6:00AM)* **

SB AHD: Work Activity:

  • Work Activity: 0) Regular Transition Shift   1) Girder Preparation    2) Girder erection Sequence 1*   3) Girder Installation** 
  • Traffic Impact: Regular TAS Plans on SB-AHD to EB-WMD exit Ramp (40km/hr regulatory signage)   1) Transition through gore to EB WMD no yielding required (TAS DWG: BF85008-TAS-RAMP-TRNS) & EB WMD Transition to SB AHD Loop Ramp Lane yielding ramp traffic [Nighttime] (EB WMD Setup ONLY – TAS DWG: BF85008S-TAS-GEP-01)    2) Ramp Lane Yielding Nighttime Closure [9:00PM-5:00AM] (TAS DWG: BF85008S-TAS-GEP-01)*      3)  EB WMD Transition to SB AHD Loop Ramp Lane [Nighttime]. (TAS DWG: BF85008S-TAS-GEP-01)**
  • Duration: March 5th  –  March 30th    1) March 8th & 9th (8:00PM – 6:00AM)    2) March 15th (8:00PM – 6:00AM)*     3) March 16th (8:00PM – 6:00AM)**

NB AHD: Work Activity:

  • Work Activity: 0) Regular Transition Shift   1) Girder Preparation    2) Girder erection Sequence 1*   3) Girder Installation** 
  • Traffic Impact: Regular TAS Plans on SB-AHD to EB-WMD exit Ramp (40km/hr regulatory signage)   1) Transition through gore to WB WMD no yielding required (TAS DWG: BF85008-TAS-RAMP-TRNS) & WB WMD Transition to NB AHD Loop Ramp Lane yielding ramp traffic [Nighttime] (TAS DWG: BF85008S-TAS-GEP-01)    2) Ramp Lane Yielding Nighttime Closure [9:00PM-5:00AM] (TAS DWG: BF85008S-TAS-GEP-01)*      3)  WB WMD Transition to NB AHD Loop Ramp Lane [Nighttime]. (TAS DWG: BF85008S-TAS-GEP-01)**
  • Duration: March 5th  –  March 12th    1) March 10th & 11th (8:00PM – 6:00AM)    2) March 15th (8:00PM – 6:00AM)*     3) March 16th (8:00PM – 6:00AM)**

WEDGEWOOD CREEK STRUCTURE LOCATION:

Southbound AHD:

  • Work Activity Bridge Construction -TAS Plan (TCS-B-1.20B REV 03) fully active
  • Traffic Impact: During work hours speed 60km/hr (During nonwork hours – speed posted 80 km/hr) Weekends remain 80km/hr unless update provided & Structure Width restriction to 9.4 m
  • Duration: February 18th –  March 5th

Northbound AHD:

  • Work Activity Bridge Construction -TAS Plan (TCS-B-1.20B REV 03) fully active   /     Reinstalling Debris Netting
  • Traffic Impact: During work hours speed 60km/hr (During nonwork hours – speed posted 80 km/hr) Weekends remain 80km/hr unless update provided & Structure Width restriction to 9.4 m.   //   Single right lane closure daytime
  • Duration: February 18th –  March 5th    //   March 1st  (9:30AM – 3:00PM)

NORTH SASKATCHEWAN RIVER STRUCTURE LOCATION:

Southbound AHD:  N/A

Northbound AHD:  N/A

Check 511 for more information

311 CITY OF EDMONTON 

https://www.edmonton.ca/programs_services/311-city-services.aspx

511 ALBERTA

https://511.alberta.ca

CONTACT US

Project Manager: Rodney Allain
rodney.allain@carmacksent.com
780 – 955 – 5545

Communications: Darrell Trapp
darrell.trapp@carmacksent.com
780 – 955 – 5545