HWY 689 BRIDGE OVER BEATON CREEK

PROJECT OWNER: Alberta Transportation
PROJECT LOCATION: Hwy 689 over Beaton Creek west
PROJECT SCHEDULE: July 2016 to August 2017
PROJECT VALUE: $2,218,526.88

Alberta Paving

PROJECT DESCRIPTION:

The scope of this project included replacing the existing bridge and related roadwork. Specifically, the work included constructing a temporary detour, demolition of the existing bridge, reconstruct the banks of the creek below the new bridge and construct a new 16m single span bridge. The bridge includes cast-in-place abutments, 9-16m long precast girders, an HPC deck overlay, waterproofing and asphalt surfacing. Main roadwork quantities include: 18000 m3 of borrow excavation, 3910 tonne of GBC and 1900 tonne of ACP.