Print Friendly, PDF & Email

HIGHWAY 1 EB OVER SWIFT CURRENT CREEK

PROJECT OWNER: Saskatchewan Ministry of Highways & Infrastructure
PROJECT LOCATION: Hwy 1, on the east limits of Swift Current, SK
PROJECT SCHEDULE: March 2017 to July 2017
PROJECT VALUE: $1,638,761

PROJECT DESCRIPTION:

This project involved the demolition of the existing superstructure, modifications and repairs to the existing bridge substructure and construct a new superstructure, including precast concrete box girders, a cast-in-place concrete bridge deck, bridge deck waterproofing and an asphalt surface course. The bridge is a 56m long, four span structure. The project is located on the Trans-Canada Highway on the east limits of Swift Current. 